Team,

 

I am running perfomance based for some fleets.PM is setup for 350 / 2750 hours strategy based.  The current counter reading is 178 hours,but when i schedule the plan on 1/12/2015 the system released a work order immediately....Am not sure how? because we expect the PM at 350 hour....


Annual perfomance is 6000 hours
PM setup for 350/2750 hours
Total counter reading 178 hours

 

Measuring documents


178.00  38984 2015/01/16
162.00  38984 2015/01/07
135.00  38984 2014/12/29
121.00  38984 2014/12/18
110.00  38984 2014/12/11
105.00  38984 2014/12/04
104.00  38984 2014/11/27
99.00   38984 2014/11/20
57.00   38984 2014/11/12
43.00   38984 2014/11/06

 

I have another pm for which the counter reading is only 10 hour and system released PM already, but the mainteanance want their pm only at 350 hours....Is this something to do the way we use the measuing document?

 

Another issue is.....

 

- The system calculates and gives a scheduled hold for February (ex : current counter is 300hour...system expects the work order to be in febraury)....but we never entered any counter after that....Now we run IP30 for next 8 weeks and IP30 releases the scheduled hold call on February even though counter is at 300 hour. How to avoid this situation?

 

Help appreciated

 