Hi, ML friends!
There is a Cost Component Structure - 20. For this Cost Component Structure are active following indicators:
- Active;
- Primary Cost Component Split.
Cost Component Split is active for plant XXXX.
On plant XXXX we produce products, including products A and B. These products are similar to each other. For them:
- Material ledger is active;
- Indicator price determination = 3;
- Indicator price control = S.
And both of these materials have the same Valuation class.
Materials are produced from CO-PP order. Debits of this order is generated by the operation of Indirect activity allocation. Report on the Cost Component Split by Cost Center Sender shows Cost component Slpit 20 is correct.
After the operation, closing the period July 2013 we have the following result:
- For material A expenses divided by all elements of the Cost Component Split
- For material B all costs were only in one element of Cost Component Split
The total amount of price for both materials is correct.
Tell me, please, why on different materials, we see different Cost Component Split?
Thanks for attention.